Hickory West Garage Work Begins August 14
08/09/2024
As part of SLU's ongoing garage repairs, work will be taking place in Hickory West garage, beginning with a closure of the affected area on Wednesday, Aug. 14, 2024.
The area of work will be on the middle ramp of Hickory West garage ( connecting level 2 to level 3) including at the top and bottom of the ramp. This work area will be done in multiple phases to allow continuous access to all levels of the garage.
Safety is SLU's number one priority and so the immediate work area as well as parking adjacent to the work area will be blocked during the work. Again, the contractor will be phasing this work in order to allow for continuous use of all levels of the garage to minimize disruptions. The planned phases will occur in the following order:
1A
1B
2A
2B
The entire project is estimated to take 2 to 4 months. SLU Construction Services apologizes for any inconvenience this causes as we work to maintain and improve our campus structures.
Phase 1A
Phase 1B
Phase 2A
Phase 2B